The company name has been anonymised; the focus is on how operations changed after the project.
Operations before the project
The company invests in and installs rooftop solar systems on factories under long-term agreements with factory owners.
Bottlenecks that led the business to Justeps
- The company wanted to join a PPP project but was unclear on financial capacity and experience requirements.
- It needed a consortium partner but had no consortium agreement.
- The draft project contract's revenue risk-sharing mechanism had not been analysed.
Steps Justeps took with the business
- Compared the company's capacity with tender requirements under PPP and bidding laws.
- Drafted a consortium agreement splitting scope, capital and liability.
- Analysed the project contract and proposed clarifications.
- Supported the legal part of the bid.
How operations changed
- The bid met the legal requirements.
- The consortium relationship was clear from the start.
- The company understood the risks before committing capital.
Lesson learned: for Energy businesses, standardisation should start with the highest legal risks and then extend to the whole system so that operations are not disrupted.
Laws applied
- Law on Public-Private Partnership Investment No. 64/2020/QH14
- Law on Bidding No. 22/2023/QH15
Related Justeps service
Public-private partnership. Learn about the service
If your business faces similar bottlenecks, send a request to info@justeps.vn or Hotline/Zalo +84 961 722 607.
Contact Justeps
📩 Email: info@justeps.vn
☎️ Hotline/Zalo: 096 172 2607
📍 Thanh Xuan office: 12th floor, Licogi 13 Tower, 164 Khuat Duy Tien, Thanh Xuan ward, Hanoi
📍 Ha Dong office: LK06B, No.10, Dong Dua area, Ha Dong ward, Hanoi
📍 Ho Chi Minh City branch: 528 Le Van Sy, Nhieu Loc ward, Ho Chi Minh City (formerly Ward 14, District 3)
📍 Hai Phong office: Truong Thinh hamlet, Ha Dong commune, Hai Phong
📍 Quang Ninh office: Van Don special zone, Quang Ninh